Rougemont-1

  • Sitio Francia
  • Energía Energía eólica
  • Cliente Électricité de France (EDF)
  • Estado In operation
  • Poner en funcionamiento 2017
  • Adquisición 2017
  • Vencimiento de PPA 2032
  • Potencia bruta instalada 36.1
  • Participación Innergex (%) 70
  • Asociación Crédit Agricole Assurances
Located in the Bourgogne-Franche-Comté region of France, the Rougemont-1 wind farm consists of 13 GE wind turbines, each with a gross capacity of 2.78 MW. Its commissioning activities began in May 2017. All the electricity produced by this wind farm is sold under a power purchase agreement (PPA) at a fixed price of which a portion is adjusted according to inflation indexes, for an initial term of 15 years, with EDF. The PPA comes to term in 2032. The Rougemont-1 wind farm’s average annual production is estimated at 84,720 MWh.
Partnership
Crédit Agricole Assurances owns a 30% interest in the facility since October 26, 2023.