Douglas Creek

Energy Hydroelectricity
Status In operation
Commissioned 2009
Acquisition 2011
PPA expiration 2049
Innergex participation (%) 50.0
Capacity - gross (MW) 27.0
Capacity - net (MW) 13.5
Client BC Hydro
Partner CC&L Harrison Hydro Project Limited Partnership and LPF (Surfside) Development L.P.

Project

The Douglas Creek Project is a run-of-river hydroelectric facility with an installed capacity of 27 MW and an estimated yearly energy output of 92.6 GWh.

Construction of the Douglas Creek Project facility commenced in May 2007 and the COD was achieved on October 19, 2009.

Douglas Creek uses the hydraulic resources of the lower reaches of Douglas Creek, with the point of diversion 3.1 km upstream from the powerhouse, which in turn is 1 km upstream of the confluence of Douglas Creek with Little Harrison Lake.

The Douglas Creek plant has been granted with ECOLOGO® certification, the only independent recognized environmental standard, for its reduced impact on environment.

ECOLOGO_RGB_Green
PRODUCT CERTIFIED FOR REDUCED ENVIRONMENTAL IMPACT. VIEW SPECIFIC ATTRIBUTES EVALUATED: UL.COM/EL
CCD 003

Partnership

In 2011, Innergex announced the acquisition of Cloudworks Energy Inc. Cloudworks’ portfolio of assets consisted of an interest of 50.01% in six run-of-river hydroelectric facilities, the remaining 49.9% being owned by CC&L Harrison Hydro Project Limited Partnership and LPF (Surfside) Development L.P.

The Harrison Operating Facilities consist of six run-of-river hydroelectric power facilities located near Harrison Lake in southwestern British Columbia that were commissioned in 2009 and 2010: Douglas Creek, Fire Creek, Stokke Creek, Tipella Creek, Upper Stave River and Lamont Creek. These facilities have a total installed capacity of 150 MW which, based on long-term average hydrology, produce 594 GWh of energy annually.